01 Sep *OLD – Giordano Industrial Completes Five BlenZer System Installations for Statco-DSI
Giordano Industrial coordinated complex equipment integration across active beverage production facilities in New York and New Jersey.
Five Projects. One Proven Partner.
Across a five-project installation program for Statco-DSI, Giordano Industrial integrated BlenZer systems into high-throughput beverage production operations throughout New York and New Jersey. Each project required the coordinated management of complex construction and equipment integration while controlling downtime within active production environments.
Project Timeline
The installation program began in January 2025, with additional projects completed in March 2025, May 2025, November 2025, and January 2026. The May installation took place at a facility in Morristown, New Jersey, while the remaining four projects were completed at Liberty Coca-Cola Beverages’ production facility in Elmsford, New York.

Giordano’s Scope of Work
The equipment at the center of these projects is manufactured by Statco-DSI, a ProMach product brand specializing in sanitary processing equipment and integrated systems for the food, dairy, and beverage industries. Its BlenZer technology is a continuous inline blending system that combines precisely metered ingredient streams with automated controls to support blending accuracy, faster product changeovers, and continuous beverage production.
Across these five projects, Giordano Industrial managed the coordinated construction and installation work needed to incorporate each BlenZer system into its production environment. The work included mechanical and electrical demolition, equipment placement and installation, mechanical connections, and the installation of new electrical power and control systems. Responsibilities were coordinated around the requirements of the equipment, the conditions within each facility, and the operating needs of the production line.
Minimizing Downtime in Production Environments

This level of coordination is especially important in high-throughput beverage production. Extended downtime can reduce output, disrupt production schedules, affect downstream operations, and generate costs well beyond the immediate construction area. Demolition, equipment placement, utility connections, electrical work, and control system installation must therefore be carefully sequenced to move the project forward without avoidable delays.
Giordano Industrial brought the project controls, industrial construction capabilities, and field coordination required to manage these installations from initial preparation through final completion. Each project was executed with close attention to budget, schedule, safety, operational continuity, quality, and fit and finish.
A Trusted Partner for Complex Installations
Delivering five installations across multiple facilities and project schedules also demonstrates Giordano Industrial’s ability to produce consistent results without treating every location as interchangeable. The company applied a disciplined installation process across the program while adapting its execution to the infrastructure, production requirements, and site conditions present at each facility.
The successful completion of these projects reinforces Giordano Industrial’s position as a trusted contractor for sophisticated equipment installations within large-scale manufacturing environments. Its work with Statco-DSI demonstrates the level of planning, coordination, and execution required to integrate advanced beverage processing systems where efficiency and production continuity are essential.
Giordano Industrial is pleased to support Statco-DSI and its clients through the installation and integration of advanced beverage blending technology.